Railways probing trains’ poor maintenance and parts shortage

LAHORE: The Pakistan Railways isinvestigating the poor maintenance of locomotives and wagons, shortages of spare parts and the closure of workshops while it is also carrying out the projects to upgrade major railway corridors with the support of the Asian Development Bank (ADB) and a consortium of local banks.

‘A probe is currently underway regarding poor maintenance of the passenger coaches, freight wagons and locomotives, closure of the railway workshops and shortage of spare parts. Some wagons were operated in substandard condition because essential components were missing,’ said Minister for Railways Muhammad Hanif Abbasiwhile speaking at a ceremony after inaugurating the newly built railway bridge that was damaged by the floods in July, foreing railways to shut the train operation on the Lahore-Faisalabad track. The train operation on the track resumed after the inauguration of the bridge.

The minister said the railway bridgehad been constructed in a record time of just 45 days, 15 days ahead of the 60-day deadline. He credited the achievement to the hard work of the PR employees and effective management.

‘Around 1,500 feet of railway track was washed away by floods on July 27.

Following the completion of feasibility studies, consultancy arrangements and funding requirements, restoration work began on Sept 23 and was completed within 45 days,’ he explained, adding that the restoration would facilitate the resumption of several passenger services, including the Shalimar Express, Karakoram Express, Badar Express, Ghouri Express and Ravi Express, besides freight train 503.

Talking about the ML-1 project, Mr Abbasi said that the process for upgrading the railway track between Rohri and Karachi was underway with agreements expected to be finalised and signed in December or January. ‘Funding is also being arranged through a consortium of local banks for the approximately 449km Rohri-Multan section while the historic Rohri Junction, which is around 150 years old, would be inaugurated after its upgradation on Jan 15. The station would have modern escalators, CIP lounges and five-star-standard accommodation facilities for locomotive drivers and guards.

The minister said efforts were under way to improve the performance of railways, including its workshops, locomo-tives, passenger facilities, freight operations and infrastructure. ‘The department is currently operating an average of nine trains daily, with plans to increase the number to 14 between Jan 10 and 20.

He said 43 GEU-43 locomotives were operating with only two or three traction motors instead of the required six, affecting their capacity to haul 3,400 tonnes.

The department had decided to restore all 43 locomotives to full operational capacitybyDec15.

According to him, a comprehensive technical assessment of passenger coaches had also been completed to identify and rectify defects. Similar assessments would now be conducted of freight trains, rolling stock and railway tracks.

Regarding the revival of workshops, Mr Abbasi said the CDL workshop had remained closed for the past 15 years, while its wheel machine had become dysfunctional in 2007-08. The facility had previously manufactured 253 different items, but production had almost come to a standstill.

He said the government was working to restart local manufacturing of essential railway components to reduce dependence on imports while production of safety brackets and other necessary partshad alreadybegun.

Modern facilities had also been introduced at railway stations in Rawalpindi, Khanewal, Lahore and Kotri, while projects for Taxila, Rawalpindi and otherstations were under way or at the tendering stage, he informed.

On railway crossing safety, the minister said the Punjab Chief Minister Maryam Nawaz assured him of giving Rs3bn to railways next week for safety measures. ‘The overall project has an approved allocation of approximately Rs9.7bn, with its first phase targeted for completion by March 30,’ he said.

According to the minister, the provision of Rs5bn during the current financial year and another Rs5bn in the next fiscal year would significantly reduce accidents at railway crossings. The Punjab government had also assured railways of providing Rs5bn for upgrading eight branch railway routes, where diesel multiple unit (DMU) trains had been planned to operate.

About digitalisation and outsourcing, the minister said that the PR would complete its digitalisation process by Dec 31.

The system would enable real-time monitoring of train movements, locations and speeds, as well as information about derailments and accidents.

The minister also announced that hepatitis screening would be conducted for around 60,000 PR employees and 3,500 railway police personnel. Special arrangements would be made for the free treatment of employees diagnosed with the disease.

For the first time, he said the PR has set a target of selling scrap worth approximately Rs10bn during the current year.