THE federal government’s plan to install 18MW of rooftop solar on 499 government buildings in Gilgit-Baltistan (GB) by December this year is a welcome step.
However, the plan on its own would not end the menace of loadshedding in the region.
According to the GB Water and Power Department, floods since June have reduced the region’s hydropower capacity from 211.6MW to about 157MW, against a summer demand of 285MW. In one season, climate change took away roughly 55MW, which is three times more than what the solar programme would add.
The cheapest megawatt is the one that is recovered from a power plant that already exists. Gilgit city has about 70MW of installed capacity, but generates only around 33MW in winter. Worn-out turbines, silted intakes, weak lines and faults that wait weeks for outside repair teams account for much of that loss. Repairing these plants, and traininglocaltechnicians to maintain them, should come before any new plan is set in motion.
As for the solar option, the output must reach homes, schools and clinics, not just government offices. Besides, battery back-ups are critically important. The regional grid project linking Gilgit, Hunza, Astore and Skardu, approved by the Executive Committee of the National Economic Council in 2023, must also be completed so that surplus power in one valley can serve another.
Reliable clean power would also mean fewer diesel generators and wood fires in a region whose glaciers feed the Indus.
The people of GB need repairs first, solar next, and finally a connected grid.