PESHAWAR: The completion of Warsak Canal remodelling project will secure 0.45 million acre-feet of additional annual water rights from the transboundary Kabul River, generating more than Rs62.4 billion in annual economic value for Khyber Pakhtunkhwa.
The adviser to the governor on irrigation, Dr Mohammad Irshad, on Thursday told journalists that the planning and development department agreed to increase the project’s funding from Rs650 million to Rs1.5 billion, spearheading efforts to clear financial hurdles and fast-track execution of the scheme.
He said that Rs260 million had already been released against liabilities of Rs800 million. He said that the remaining balance of Rs390 million was released months ahead of its January deadline and paid out to project contractors, including the Chinese executing firm, settling a major chunk of partial liabilities.
Dr Irshad said that they took up the issue of funds and allocation enhancement as they were focusing on high priority projects that served the interest of a large number of people. He said that fiscal space for the high priority projects would be created by rationalising politically motivated and low impact schemes.
The adviser said that under the project, the department brought 8,000 acres of barren land under irrigation so far and 5,000 additional acres would also be irrigated after its completion, extending the farthest reaches of canal system to Jalozai area of Nowshera district.
He said that following the completion of the project, water allowance or number of cusecs of water per 1,000 acres would go up from existing four to 9.4 cusecs for gravity canal and 3.7 to seven cusecs on lift canal.
Irrigation department officials in their briefing on the occasion said that the Warsak canal system was commissioned in the 1960s for irrigating 94,913 acres of land across the districts of Peshawar, Khyber and Nowshera.
They said that the Warsak Canal remodelling project, on the other hand, was conceived to alleviate tail-end water shortages, provide drinking water and establish enhanced water rights over the Kabul River. They said that it was categorised as a high-priority project by the KP government.
The project entails construction of 5.2 kilometres long auxiliary irrigation tunnel for 700 cusecs capacity from Warsak Dam. In addition to this, Warsak gravity and lift canals, both built in the 1960s, have been remodelled.
‘Warsak gravity canal remodelled from 285 to 456 cusecs, [while] lift canal remodelled from 200 to 290 cusecs,’ an irrigation official said.
Besides the remodelling, the existing pump house is being upgraded and a new pump house is also being constructed for lifting of additional 90 cusecs.
To meet the additional power requirements for the project, the existing 66kv grid station is being upgraded to 132kv along with high tension lines for the pump house.
The officials said that the existing canal capacity stood at 550 cusecs, 350 cusecs for the Warsak gravity and 200 cusecs for lift canals.
However, the remodelling will add another 700 cusecs including 300 cusecs for the drinking water supply of the provincial capital besides providing additional 176 cusecs for Warsak gravity canals and 90 cusecs for Warsak lift canal.
They said that the construction of 5.2 kilometres long auxiliary tunnel was launched in March 2023 with a projected completion timeline of 4.5 years. It will be completed in September 2027 at a cost of Rs6.6 billion. According to them, so far a four kilometres long tunnel has been excavated.
They said that following the completion of the project, cropped area would increase from 75,463 acres to 117,952 acres, registering an increase of 42,489 acres.
Similarly, the orchard area will also increase from existing 8,350 acres to 16,733 acres whereas fruit production will also reach 46,064 tonnes per annum from the existing 19,702 tonnes.
Officials said that it would also result in additional annual crop production of 78,024 tonnes of fodder, 87,513 tonnes of sugarcane, 4,271 tonnes of wheat and 6,242 tonnes of maize. ‘Estimated annual benefits upon the completion of the project are Rs5.6 billion,’ an official said.
In addition to this, 300 cusecs have been allocated as a sustainable source of drinking water for 3.2 million people of Peshawar and nearby areas. The project will also help to stop depletion of the city’s underground water table as over 300 tubewells would be closed down.