LAHORE: Residents of the Gharibwal village have demanded construction of a bridge over the Jalalpur Canal to maintain access to their homes, agricultural land and traditional grazing grounds, opposing excavation of a remaining stretch of the canal without a crossing facility.
Daman Lok Perhoo, a people’s assembly of villages along the canal, has urged the irrigation department and local administration to stop threatening residents with police action and legal proceedings for resisting the excavation.
In a statement issued on Thursday, the assembly said residents received fresh warnings from the irrigation department, police and local administration on Nov 18, asking them to end their protest or face coercive and legal action.
The dispute centres on an unexcavated section of the canal that provides the last direct link between Gharibwal village and its grazing land on the northern side.
According to the assembly, excavation without first constructing a bridge would cut off hundreds of residents from their land and force schoolchildren to travel an additional 10 kilometres each way to reach their schools.
It said the grazing grounds were essential to local livelihoods, as families had traditionally taken their cattle, goats and sheep to the pastures for generations. The canal had separated settlements from these areas, while the existing crossing points were located far apart.
The assembly, which held a meeting in Gharibwal on Nov 15, said it had approached the Asian Development Bank (ADB), which finances the project, and its project director to seek intervention.
It demanded that the irrigation department and local administration provide a written guarantee, with a specified completion date, for construction of the bridge and refrain from police operations, forced excavation or legal proceedings against protesting residents.
The assembly also sought full compensation for acquired land at its actual replacement value, along with public disclosure of payments, including the names of beneficiaries and amounts paid.
It asked the ADB to take up the matter with the project director, communicate its position in writing before any action on the ground and arrange an independent review of land compensation under the bank’s resettlement policy. It also called on the bank to ensure a safe environment for dialogue before asking the community to use its grievance redressal mechanism.
According to the irrigation department, the Jalalpur Irrigation Project aims to develop around 169,000 acres in Pind Dadan Khan and Khushab tehsils. The revised project cost is Rs3.959 billion, with the Asian Development Bank contributing Rs2.624 billion.
Responding to a query, Pind Dadan Khan Assistant Commissioner Ayesha Shafqat said the demand for the link bridge had already been accepted. She said a feasibility report had been forwarded through the DC office to the JIP authorities, and construction would begin once funds were released.
JIP Project Director Waheed Ashraf said: ‘The district administration recommended a bridge on the demand of the community and it will be constructed after approval of the competent authority. The issue has been resolved amicably with the consent of the community.’
Asked about the blocked culverts, he said: ‘The project is under construction. The culvert will be cleared after connectivity of the full channel.’