Long-awaited GB hydel project becomes operational

GILGIT: More than a decade behind schedule, the 16-megawatt Naltar Phase-III hydropower project in Gilgit became operational on Sunday, with Gilgit-Baltistan Chief Minister Amjad Hussain vowing to end the region’s energy crisis within five years.

Speaking during a visit to the facility, where water and power department officials briefed him on electricity supply to Gilgit city, the chief minister said the newly launched project provides eight to nine hours of additional power to residents, helping reduce ongoing loadshedding.

He said he had requested Prime Minister Shehbaz Sharif to formally inaugurate the project soon. Recalling its prolonged delays, Mr Hussain noted that Naltar 14MW Phase-II and 16MW Phase-III hydropower projects were included in the Public Sector Development Programme (PSDP) in 2009 and launched in 2012, undergoing three revisions.

Progress stalled at just 3 per cent by 2015 and remained at 23pc through 2024 before accelerating to 72pc in 2025 and reaching completion.

Looking ahead, the chief minister emphasised that broader regional initiatives remain vital for a permanent solution.

‘The 40-megawatt Hanzel hydropower project has remained stalled for the past seven years, and its tendering process will be initiated again within the next three months to ensure its completion and uninterrupted electricity supply to the city,’ he said.

Hussain added that issues relating to the 54-megawatt Attabad project have been resolved, while serious efforts are underway to complete the Harpo and Shagarthang hydropower projects.—Jamil Nagri