Pakistan has a remarkable ‘love affair’ with hydropower, one that has survived cost overruns, construction failures, prolonged shutdowns and the risks of building concrete behemoths in some of the world’s most hazardous terrain.
The latest disaster at the Tarbela-5 construction site raises a fundamental question: why does an investment model that promises cheap and clean electricity repeatedly deliver expensive, delayed and unreliable infrastructure vulnerable to climate-related hazards?
The scale of Pakistan’s hydropower commitment is mind-boggling. The Integrated Generation Capacity Expansion Plan (IGCEP) 2025–35 envisages approximately 11,000 MW of additional hydropower capacity, around 34pc of all planned additions, compared with 26pc for wind and solar combined. This means committing scarce public resources to decade-long investments in geographically fixed infrastructure, even as cheaper and adaptable renewables are available. With substantial capacity surpluses and growing questions about economic viability of new centralised generation, giving large hydropower a privileged position in energy planning makes no sense.
The latest Tarbela incident adds to an already extraordinary record of cost escalation and construction failures. The estimated cost of the 1,530 MW Tarbela-5 Extension has risen from Rs82 billion in 2016 to Rs317bn by 2025, following last year’s damage. The latest setback could push the total even higher, likely five to six times the original estimate. Last year’s damage was attributed to ‘unauthorised design changes,’ and the latest damage, apparently caused by rock collapse, raises questions about geological assessment and construction management.
Tarbela-5 was supposed to generate electricity at Rs28 per unit, but further cost escalation will push it beyond the established benchmark for hydropower. This is particularly difficult to justify when the project is an extension to an existing dam.
The Tarbela project encountered serious problems from the outset. In 1974, Tunnel 2 collapsed, Tunnel 1 suffered severe damage, and the outlet structures of Tunnels 3 and 4 were also damaged. Hundreds of sinkholes appeared in the dam’s upstream impervious blanket, while erosion damaged the spillway flip bucket and plunge pool. Repairs lasted a decade. Costs rose from $828 million to about $1.5bn. Fifty years later, Tarbela remains a reminder that the cost of building a dam does not end with its construction.
Neelum-Jhelum offers an even more consequential example of getting project costs and engineering risks wrong. Originally estimated at about Rs40bn, it eventually cost Rs500bn. Cracks in the tailrace tunnel forced a 13-month shutdown in 2022-23, while sections of headrace tunnel collapsed forcing the plant offline in May 2024. Consumers had already paid estimated Rs75.5bn through a dedicated electricity surcharge, and hundreds of billions in expensive replacement electricity costs. Instead of strengthening energy security, it has become a major fiscal liability.
Dasu appears to be following a familiar trajectory. Stage-I costs have risen from Rs486bn to Rs1.73 trillion. Completion has been pushed back to November 2028, unlikely to be met. The project’s location along the Indus, with exceptionally difficult geological conditions and exposure to landslides, earthquakes and other hazards, makes construction particularly challenging. Its main funder, the World Bank, has characterised the project as ‘high risk, high reward,’ and continues to authorise more loans and extensions for another vulnerable dam. The most troubling aspect is that these problems reflect the formidable geological conditions of the Karakoram-Himalayan region, compounded by technical and institutional weaknesses in project planning and execution. Yet Pakistan continues to build a cascade of dams across the Indus, Swat, Kunhar and other rivers. Recent dam failures in India and devastating glacial and debris floods in Nepal offer further warnings about how rapidly cascading risks can overwhelm infrastructure and devastate entire river valleys.
Pakistan has already experienced what these risks can mean. The 2022 floods in Swat demonstrated how rapidly sediment, boulders, and debris can transform river channels, overwhelm infrastructure, and devastate communities. Yet the World Bank is funding four large dams in a small 45 km stretch of the river under the Khyber Pakhtunkhwa Hydropower and Renewable Energy (KHRE) programme. Local concerns have forced it out of the Madyan project, but Gabral-Kalam and Matiltan have picked up pace, while Korean investors are eyeing two more dams in the valley.
Climate projections point towards increasing extreme flood magnitudes and debris-flow risks across the Swat, Kunhar and Upper Indus basins.The problems extend well beyond engineering and construction. Social and environmental impact assessments and mitigation plans routinely underestimate the consequences of hydropower development, particularly cumulative and downstream impacts. Tunnels can dry streams. Communities continue to protest inadequate land and resettlement compensation, exclusion from project benefits, lost livelihoods and ecological damage. Landless groups and downstream communities are frequently excluded from mitigation altogether, despite evidence that downstream-affected populations can be 10 times larger than those within officially designated project impact areas. This is the deeper problem with Pakistan’s hydropower investment model. Project appraisals treat individual risks as manageable technical problems, while largely ignoring cumulative exposure across entire river basins.
When projects fail, the institutional response is remarkably consistent: revise the PC-I, increase costs, extend deadlines and secure additional financing. The underlying investment model remains untouched. What is never seriously considered is whether the decision to build was justified. The familiar claim that hydropower is cheap and green becomes difficult to sustain when these costs are considered. Cheap compared with what? Project tariffs rarely reflect the full economic costs of construction delays, financing, cost overruns, replacement generation, transmission infrastructure, resettlement and lost livelihoods. Nor do they account for the plants that remain out of service for years after commissioning. Green compared with what? A hydropower plant is not simply a turbine producing electricity. It fundamentally alters a river: interrupting sediment flows, changing downstream ecology, affecting fisheries and livelihoods, transforming flood regimes and displacing communities. The cumulative impacts of multiple dams, barrages, and diversion structures cannot be understood, let alone mitigated, by assessing each project in isolation. Pakistan needs a reliable and affordable energy system, but that does not make every proposed hydropower project a national necessity. Nor are all engineering risks manageable, cost overruns acceptable, or environmental and social damage inevitable. The next dam is not inevitable. It is a political and financial decision. After Tarbela, Neelum-Jhelum, Dasu and the mounting evidence of risks across the Himalayas, let’s abandon this ‘toxic romance’ with hydropower. The question is what kind of energy system we can afford, sustain and govern without transferring its costs to riverine communities, provincial economies and future generations.
The writer teaches at Quaid-i-Azam University and researches water, energy and development