Page 21 · Metro - Islamabad

PPRA points out procedural flaw in CDA’s sewage treatment plants

ISLAMABAD: The Public Procurement Regulatory Authority (PPRA) has pointed out a procedural deficiency in the bidding procedure for the Sewage Treatment Plants (STPs) project and directed the Capital Development Authority (CDA) to provide details of the bidding process to an appellant - a Joint Venture (JV) which was technically disqualified by CDA.

A joint venture of Elite Engineering - Orient Water Technologies - approached PPRA against the Grievance Redressal Committee (GRC) of the CDA for dismissing their applications.

After a hearing, three-member committee headed by PPRA Managing Director Hasnat Ahmed Qureshi pointed out that GRC had failed to record a satisfactory and reasoned determination regarding the disclosure issue despite having considered the matter during its proceedings. Such omission constitutes a procedural deficiency warranting interference to the limited extent of the relief sought by the appellant, said the committee order.

The appellant contended that its grievance had been misconstrued, as it neither sought preferential treatment nor disclosure of proprietary designs, trade secrets or commercially sensitive information of competing bidders. Rather, it sought disclosure of the basis of technical acceptance of competing bids. The company argued that disclosure of aggregate marks alone does not establish how the prescribed evaluation criteria were applied.

‘The PPRA’s committee pointed out it failed to adequately demonstrate compliance with Rule 35 of the PP Rules 2004, read with Clause 10 of the prescribed Technical Evaluation Report Form. Furthermore, the GRC failed to record a satisfactory and reasoned determination regarding the disclosure issue despite having considered the matter during its proceedings.’

PPRA directed the CDA to share the required details of STP-3 with the applicant, bidder-wise technical evaluation particulars of all participating and technically accepted bidders and the basis of technical acceptance under Clause 10 of the Technical Evaluation Report Form, in accordance with Rule 35 of the PP Rules, 2004.

Recently, the CDA opened financial bids for awarding the contract of STPs project aimed at stopping the flow of untreated sewage into Rawal Dam.

The project, which involves the construction of three plants to treat wastewater flowing into the Korang River and other streams, was proposed several years ago.

However, only limited funds were allocated every year, and the project has yet to be formally launched. According to budget documents, the total cost of the project is Rs6.07 billion, while the federal government has earmarked Rs449 million for the fiscal year 2026-27. The level of funding suggests that even if the project is launched in the current fiscal year, its completion will take considerable time.

Sources in the CDA said initially the civic agency was likely to start work on one treatment plant in Banigala. For the STP 3, which will be set up in Banigala on Korang Nullah and which the CDA wants to start on priority, KAPEC-Matracon submitted the lowest bid of Rs3.2 billion.

A former member of the CDA, speaking to Dawn, said there should be proper networking for the plants to avoid sludge, silt and solid material, adding heavy silt can settle inside the treatment units, disturbing the biological treatment process.