ISLAMABAD: The construction of buildings for 11 police stations in Islamabad is facing delays or slow progress with several projects also awaiting approval of revised cost estimates and variation orders, Dawn has learnt.
A total of 10.31 kanals has been allocated for the Nilore police station at Lehtrar Road. The project’s original cost of Rs81.15 million was revised to Rs107.68 million. Construction work commenced on November 27, 2025, but a completion date has not yet been provided.
So far, Rs45.95 million has been spent on the project. However, a variation order has been awaiting approval since May 18, 2026.
The Koral police station is being constructed on four kanals allocated at Gulberg Greens at an estimated cost of Rs93.48 million. Work commenced on December 12, 2025, but a completion date has not yet been specified.
So far, Rs30.46 million has been spent. However, a variation order amounting to Rs13.679 million is awaiting approval.
Similarly, 3.2 kanals has been allocated for the Sangjani police station at C-16 Markaz. The project’s original cost of Rs71.70 million was revised to Rs83.40 million.
Construction work began on December 24, 2025, but a completion date has not yet been announced. An amount of Rs35.7 million has been spent on the project.
A variation order has been awaiting approval since August 2026. The project is also facing slow progress.
The Phulgran police station is being constructed on 13.27 kanals allocated at Green Enclave-I at an estimated cost of Rs80.50 million. Construction began on December 13, 2025, and Rs24.501 million has so far been spent. The project is also facing slow progress.
Meanwhile, four kanals has been allocated for the Shams Colony police station at I-12 Markaz at an estimated cost of Rs72.22 million. Construction work commenced on January 15, 2026, but without a fixed completion date.
The Humak police station is being constructed on 4.83 kanals at Grace Valley worth about Rs71.91 million. Work began on January 19, 2026, and Rs27.86 million has so far been spent. The project is also facing slow progress.
The Khanna police station is being constructed on 6.5 kanals at Rehman Enclave at an estimated cost of Rs72.65 million. Construction began on November 27, 2025, but a revised completion date has not been provided.
The Loi Bher police station is being constructed on 6.57 kanals at Capital Enclave at an estimated cost of Rs91.40 million.
Work started on January 3, 2026, and Rs22.04 million has so far been spent.
The Golra police station is being constructed within the premises of the existing facility. The original project cost of Rs88.5 million was later revised to Rs98.912 million.
The Women Police Station is being constructed in G-7 Markaz, near its old building. The project’s original cost of Rs93.128 million was revised to Rs108.757 million.
Construction on Kirpa police station commenced on December 30, 2025.
The original project cost of Rs73.729 million was revised to Rs94.49 million.
A completion date has not been provided, while Rs32.52 million has so far been spent. A variation order for the project has been awaiting approval since September 16, 2026.